ISO 21502:2020 Clause 7.2.2 Developing the plan

Planning should be a collaborative activity, where possible, involving team members advising on planning their work. Estimates should be justifiable. A plan can include:
a) benefits to be realized.
b) scope: outputs and outcomes to be delivered, taking quality into account.
c) resources needed, such as people, materials, tools, equipment and other organizations.
d) schedule: when activities are to be done.
e) cost.
f) risks inherent in the plan.
g) assumptions and constraints.
Dependencies between activities and other work components (such as programmes and projects) should be defined. The plan should include and allow for assurance and decision-making activities. The plan can be based on a hierarchy showing each work component’s place in the hierarchy with single-point accountability assigned for each work package and activity. Plans should be viewable at different levels of the hierarchy and show the level of detail appropriate to the needs of those viewing the plan.
Planning should be iterative and progressive through the life cycle of a project, with more detail for the immediate future than for more distant work. As work progresses, scope can be refined and clarified, to develop a plan which can be delivered at an acceptable level of risk. A plan may include an indication of the current level of certainty by, for example, using ranges or confidence indicators.

Developing a comprehensive project plan is a crucial step in project management, and it requires careful consideration and collaboration among key stakeholders. Here’s how an organization can develop a plan effectively:

  1. Clearly articulate the goals and objectives of the project. Ensure that objectives are specific, measurable, achievable, relevant, and time-bound (SMART).
  2. Involve relevant stakeholders throughout the planning process to ensure that their perspectives, needs, and expectations are considered. Stakeholders may include project sponsors, clients, end-users, project team members, and other relevant parties.
  3. Gather requirements by conducting interviews, workshops, surveys, and other techniques to understand the needs and expectations of stakeholders. Document requirements thoroughly to ensure that they are captured accurately.
  4. Define the scope of the project by identifying what is included and excluded from the project. Develop a detailed scope statement that outlines project deliverables, requirements, constraints, and assumptions.
  5. Decompose the project scope into smaller, manageable tasks and subtasks using a hierarchical structure known as the Work Breakdown Structure (WBS). Organize project work into logical components to facilitate resource allocation, scheduling, and tracking.
  6. Estimate the human, financial, material, and equipment resources required to complete the project. Develop resource plans that allocate resources based on project requirements, availability, and constraints.
  7. Develop a project schedule that defines the start and finish dates for each project task and milestone. Use scheduling techniques such as Gantt charts, network diagrams, and critical path analysis to sequence tasks and allocate resources effectively.
  8. Identify potential risks and uncertainties that may impact the project’s objectives, schedule, budget, or quality. Develop risk registers that document identified risks, their likelihood and impact, and proposed risk response strategies.
  9. Define quality standards and acceptance criteria for project deliverables. Develop a Quality Management Plan that outlines quality assurance and quality control activities to ensure that project outputs meet stakeholder expectations.
  10. Develop a Communication Management Plan that defines how project information will be communicated to stakeholders. Identify key stakeholders, their communication needs, and preferred communication channels.
  11. If the project involves procuring external goods or services, develop a Procurement Management Plan that outlines the procurement strategy, selection criteria, contract types, and vendor management processes.
  12. Develop a Change Management Plan that outlines how changes to project scope, schedule, budget, or requirements will be managed, evaluated, and approved.
  13. Ensure that all planning components are integrated and aligned with each other. Develop an Integrated Project Management Plan that consolidates all planning documents into a cohesive framework.
  14. Review the project plan with key stakeholders, project sponsors, and relevant authorities for approval. Ensure that the plan aligns with stakeholder expectations, organizational objectives, and project constraints.
  15. Document the project plan in a Project Management Plan (PMP) or equivalent document. The project plan serves as a roadmap for project execution and is used to guide project team members and stakeholders throughout the project lifecycle.

By following these steps and involving key stakeholders throughout the planning process, organizations can develop a comprehensive project plan that aligns with project objectives, meets stakeholder needs, and sets the stage for successful project execution.

Planning should be a collaborative activity, where possible, involving team members advising on planning their work.

Involving team members in the planning process is crucial for developing a comprehensive and realistic project plan. By involving team members in the planning process, organizations can leverage their collective expertise, insights, and perspectives to develop a more comprehensive and robust project plan. This collaborative approach fosters ownership, engagement, and alignment among team members, ultimately contributing to the success of the project.Here’s how organizations can develop a plan in project management:

  1. Create a culture that values collaboration and encourages open communication among project team members. Emphasize the importance of teamwork and collective problem-solving to ensure that everyone feels empowered to contribute their insights and expertise to the planning process.
  2. Identify and involve key stakeholders from various functional areas and levels of the organization who have a vested interest in the project’s success. This includes project sponsors, subject matter experts, end-users, and other relevant stakeholders who can provide valuable input and perspectives.
  3. Clearly articulate the project objectives, scope, deliverables, and success criteria to ensure a shared understanding among team members. Discuss and clarify any ambiguities or uncertainties related to project requirements and expectations.
  4. Organize brainstorming sessions or workshops with project team members to generate ideas, identify challenges, and explore potential solutions. Encourage creative thinking and constructive dialogue to foster innovation and problem-solving.
  5. Use a variety of planning techniques and tools to facilitate the planning process. This may include techniques such as mind mapping, SWOT analysis, stakeholder analysis, and decision matrices to structure discussions and prioritize activities.
  6. Collaboratively develop a Work Breakdown Structure (WBS) with input from project team members to decompose the project scope into manageable tasks and subtasks. Break down work packages into smaller, more actionable components that can be assigned to individual team members.
  7. Assign responsibilities for each work package to team members based on their expertise, availability, and preferences. Communicate expectations, deadlines, and deliverables to ensure accountability and alignment with project goals.
  8. Collaboratively estimate the resources, effort, and duration required to complete each task and work package. Leverage the collective knowledge and experience of team members to develop realistic estimates and identify potential resource constraints or bottlenecks.
  9. Collaboratively identify dependencies between tasks, as well as any constraints or limitations that may impact the project schedule or budget. Discuss strategies for managing dependencies and mitigating constraints to ensure smooth project execution.
  10. Review the draft project plan with key stakeholders and project team members to gather feedback and identify areas for improvement. Incorporate feedback and make necessary adjustments to the plan to address concerns and enhance its effectiveness.
  11. Document the finalized project plan in a formal Project Management Plan (PMP) or equivalent document. Ensure that the plan is accessible to all project stakeholders and serves as a reference point for guiding project execution and decision-making.

Estimates should be justifiable.

Justifiable estimates are essential for developing accurate and reliable project plans. By prioritizing justifiable estimates in project management, organizations can improve decision-making, mitigate risks, optimize resource allocation, and enhance project outcomes. Justifiable estimates provide the foundation for successful project execution and enable project managers to deliver value to stakeholders effectively. Here’s why estimates should be justifiable in project management:

  1. Justifiable estimates provide a solid foundation for decision-making throughout the project lifecycle. Project managers rely on estimates to allocate resources, set budgets, establish schedules, and make strategic decisions. Justifiable estimates ensure that decisions are based on realistic assumptions and expectations.
  2. Justifiable estimates help project managers identify and mitigate risks more effectively. By understanding the underlying assumptions and uncertainties associated with estimates, project managers can assess the potential impact of risks on project objectives and develop appropriate risk response strategies.
  3. Justifiable estimates enable project managers to allocate resources efficiently and effectively. By accurately estimating resource requirements, project managers can ensure that the right resources are available at the right time to support project activities. This helps prevent resource shortages, bottlenecks, and delays.
  4. Justifiable estimates form the basis for developing realistic project schedules. By estimating task durations, dependencies, and critical paths accurately, project managers can create schedules that reflect the true scope and complexity of the project. This helps ensure that project milestones are achievable and that project timelines are realistic.
  5. Justifiable estimates are essential for managing project budgets effectively. By accurately estimating costs and expenses, project managers can develop budgets that align with project objectives and stakeholder expectations. Justifiable estimates also enable project managers to track expenses, identify variances, and manage budget risks proactively.
  6. Justifiable estimates inspire confidence and trust among project stakeholders. When stakeholders understand the rationale behind project estimates and are confident in their accuracy and reliability, they are more likely to support the project and remain engaged throughout its lifecycle.
  7. Justifiable estimates provide a benchmark for monitoring project performance and progress. By comparing actual performance against estimated values, project managers can identify deviations, assess project health, and take corrective actions as needed to keep the project on track.

To ensure that estimates are justifiable in project management, project managers should:

  • Use historical data, expert judgment, and relevant information to inform estimates.
  • Break down project tasks into smaller, more manageable components to facilitate estimation.
  • Consider uncertainties, assumptions, and risks when developing estimates.
  • Document the rationale and methodology behind estimates to provide transparency and accountability.
  • Continuously review and validate estimates throughout the project lifecycle to ensure accuracy and relevance.

A plan can include benefits to be realized.

Including benefits to be realized in the project plan is essential for ensuring that the project aligns with the organization’s strategic objectives and delivers value to stakeholders. Here’s why and how benefits can be included in a project plan:

  1. Linking project activities to anticipated benefits ensures that the project contributes to the organization’s strategic goals and objectives. By explicitly stating the expected benefits in the project plan, project managers can demonstrate how the project adds value and supports the organization’s mission and vision.
  2. Communicating anticipated benefits to stakeholders fosters engagement and buy-in throughout the project lifecycle. Stakeholders are more likely to support the project and actively participate in its execution when they understand how it will benefit them or the organization. Including benefits in the project plan helps manage stakeholder expectations and maintain their commitment to the project.
  3. Identifying and prioritizing benefits helps project managers focus on delivering tangible outcomes and maximizing value for stakeholders. By defining clear, measurable benefits, project teams can prioritize activities and allocate resources effectively to achieve the desired results. This ensures that project efforts are aligned with the outcomes that matter most to the organization and its stakeholders.
  4. Incorporating benefits into the project plan facilitates benefits realization management (BRM) throughout the project lifecycle. BRM involves identifying, planning, tracking, and measuring the realization of benefits from the project. By defining benefits upfront and establishing mechanisms for tracking progress, project managers can ensure that benefits are realized in a timely and effective manner.
  5. Anticipating benefits can help project managers identify potential risks and uncertainties that may impact their realization. By conducting a benefits risk assessment, project teams can identify barriers, dependencies, and mitigating actions needed to ensure that benefits are achieved as planned. This proactive approach to risk management helps mitigate threats to benefit realization and increases the likelihood of project success.
  6. Monitoring and evaluating benefits throughout the project lifecycle provide valuable insights for continuous improvement. By tracking the actual realization of benefits against planned targets, project teams can identify opportunities for optimization, course correction, and learning. This iterative approach to benefits management enables organizations to adapt to changing circumstances and enhance their ability to deliver value over time.

To include benefits in a project plan, project managers should:

  • Identify and prioritize anticipated benefits based on stakeholder needs and organizational objectives.
  • Define clear, measurable benefit metrics and targets to track progress and evaluate success.
  • Develop a benefits realization plan that outlines the activities, responsibilities, and timelines for achieving and monitoring benefits.
  • Incorporate benefits into project objectives, scope, deliverables, and performance measures to ensure alignment and accountability.
  • Communicate the anticipated benefits to stakeholders and engage them in the benefits realization process.
  • Continuously monitor, evaluate, and report on the realization of benefits throughout the project lifecycle, making adjustments as needed to optimize value delivery.

By including benefits in the project plan and actively managing their realization, organizations can ensure that projects contribute to strategic objectives, deliver meaningful outcomes, and maximize return on investment.

A plan can include scope: outputs and outcomes to be delivered, taking quality into account.

Including scope in a project plan is essential for defining the boundaries and objectives of the project. Scope outlines the work to be performed, including both the outputs and outcomes to be delivered, while also considering quality requirements. Here’s how scope, including outputs and outcomes, can be included in a project plan:

  1. Clearly define the boundaries of the project by outlining what is included and excluded from the project. This involves identifying the specific deliverables, products, services and results that the project will produce or achieve.
  2. Specify the tangible products, services, or deliverables that the project will produce. Outputs are the tangible results of project activities and represent the physical or technical deliverables that stakeholders will receive upon project completion.
  3. Define the desired outcomes or benefits that the project aims to achieve. Outcomes are the broader, long-term impacts or changes that result from the successful delivery of project outputs. They represent the value or benefits that stakeholders expect to derive from the project.
  4. Take quality into account when defining scope by specifying the quality standards, criteria, and expectations for project deliverables. Quality requirements ensure that project outputs meet stakeholder expectations and adhere to relevant industry standards and best practices.
  5. Ensure that the scope, including outputs and outcomes, aligns with the project objectives, goals, and stakeholder expectations. The scope should reflect the intended purpose and value proposition of the project and contribute to the achievement of organizational strategic objectives.
  6. Develop a process for managing scope changes and ensuring that any changes to the project scope are properly evaluated, documented, and approved. Scope changes should be assessed for their impact on project objectives, schedule, budget, and quality to minimize scope creep and maintain project focus.
  7. Document the agreed-upon project scope, including outputs, outcomes, and quality requirements, in a scope baseline or equivalent document. The scope baseline serves as a reference point for project planning, execution, and control, providing a basis for measuring project performance and managing scope changes.
  8. Communicate the project scope, including outputs, outcomes, and quality requirements, to all project stakeholders. Ensure that stakeholders have a clear understanding of what is included in the project scope, what will be delivered, and how quality will be ensured throughout the project lifecycle.

By including scope, including outputs and outcomes, in the project plan and considering quality requirements, project managers can ensure that the project objectives are clearly defined, stakeholders’ expectations are managed, and project deliverables meet quality standards. This helps minimize misunderstandings, mitigate risks, and enhance overall project success.

A plan can include resources needed, such as people, materials, tools, equipment and other organizations.

Including resources needed in a project plan is crucial for ensuring that the necessary resources are available to execute the project successfully. Resources encompass various elements such as people, materials, tools, equipment, and external organizations. Here’s how these resources can be included in a project plan:

  1. Determine the skills, expertise, and roles required to execute the project. This includes identifying project team members, their roles, responsibilities, and reporting relationships. Consider factors such as project complexity, workload, and availability when identifying human resource needs.
  2. Assign specific individuals or roles to project tasks and responsibilities based on their skills, experience, and availability. Develop a staffing plan that outlines the allocation of human resources throughout the project lifecycle, considering factors such as workload distribution and resource constraints.
  3. Identify external organizations, consultants, or contractors that may be required to provide specialized expertise or support for project activities. Develop procurement plans, contracts, and agreements to secure external resources as needed, ensuring alignment with project objectives and budget constraints.
  4. Identify the materials, supplies, and equipment required to support project activities. Develop procurement plans, purchase orders, and contracts to acquire necessary materials and equipment, considering factors such as quality, cost, and delivery timelines.
  5. Identify the tools, software, and technology platforms needed to support project execution and collaboration. Ensure that project team members have access to the necessary tools and resources to perform their tasks effectively, including project management software, communication tools, and collaboration platforms.
  6. Take into account any limitations or constraints related to resource availability, budgetary constraints, and organizational policies when planning resource allocation. Develop contingency plans and alternative strategies to address resource constraints and mitigate potential risks to project execution.
  7. Continuously monitor resource utilization and performance throughout the project lifecycle. Track resource allocation, utilization rates, and productivity metrics to ensure that resources are being used efficiently and effectively. Make adjustments to resource allocation as needed to optimize project performance and mitigate risks.
  8. Communicate resource needs and requirements to relevant stakeholders, including project team members, resource managers, and organizational leadership. Ensure that stakeholders are aware of resource constraints, dependencies, and priorities to facilitate effective resource management and decision-making.

By including resources needed in the project plan and effectively managing resource allocation, project managers can ensure that the necessary people, materials, tools, equipment, and external organizations are available to support project execution. This helps minimize resource constraints, optimize resource utilization, and enhance overall project performance and success.

A plan can include a schedule: of when activities are to be done.

A schedule is a critical component of any project plan. It outlines the sequence and timing of project activities, helping to ensure that tasks are completed on time and that the project stays on track. Here’s how a schedule can be included in a project plan:

  1. Break down the project scope into specific tasks and activities that need to be completed to achieve project objectives. This involves creating a Work Breakdown Structure (WBS) that decomposes the project scope into smaller, manageable components.
  2. Determine the logical sequence in which project activities should be performed. Identify dependencies between tasks, such as finish-to-start, start-to-start, finish-to-finish, and start-to-finish relationships, to establish the order in which activities should be executed.
  3. Estimate the time required to complete each project activity. This involves considering factors such as task complexity, resource availability, and historical data to develop realistic duration estimates for each activity.
  4. Create a Gantt chart or similar visual representation of the project schedule. A Gantt chart displays project activities along a timeline, showing the start and end dates of each task, as well as any dependencies between tasks.
  5. Assign resources, such as personnel, materials, and equipment, to each project activity based on resource availability and skill requirements. Ensure that resources are allocated in a way that optimizes resource utilization and minimizes resource conflicts.
  6. Identify key milestones or checkpoints in the project schedule to mark significant events or achievements. Milestones represent important project deliverables, decision points, or project phases and help track progress and monitor project performance.
  7. Incorporate contingency buffers into the schedule to account for uncertainties and risks that may impact project activities. This includes adding extra time to accommodate potential delays or unexpected events that may arise during project execution.
  8. Review the schedule with key stakeholders to ensure that it accurately reflects project requirements, constraints, and priorities. Validate the schedule against project objectives and constraints, making adjustments as needed to address any concerns or discrepancies.
  9. Regularly update the project schedule to reflect actual progress and changes in project scope, resources, or constraints. Monitor progress against the baseline schedule, tracking deviations and identifying corrective actions to keep the project on track.
  10. Communicate the project schedule to all stakeholders, ensuring that everyone is aware of project timelines, milestones, and dependencies. Foster transparency and accountability by sharing schedule updates and revisions as necessary to keep stakeholders informed.

By including a schedule in the project plan, project managers can effectively plan, coordinate, and manage project activities, ensuring that tasks are completed on time and within budget. A well-defined schedule helps minimize delays, mitigate risks, and optimize resource allocation, ultimately contributing to the successful delivery of the project

A plan can include cost.

Including cost estimates and budgets in a project plan is essential for effective financial management and budget control throughout the project lifecycle. By including cost estimates and budgets in the project plan, project managers can effectively manage project finances, optimize resource allocation, and ensure that the project is completed within budgetary constraints. A well-defined cost management plan helps minimize cost overruns, maximize cost efficiency, and enhance overall project success. Here’s how costs can be included in a project plan:

  1. Estimate the costs associated with executing the project, including labour, materials, equipment, overhead, and other expenses. Use historical data, expert judgment, and cost estimation techniques such as analogous estimating, parametric estimating, and bottom-up estimating to develop accurate cost estimates for each project activity.
  2. Develop a cost baseline that outlines the total budget for the project, broken down by cost categories, phases, or work packages. The cost baseline serves as a reference point for comparing actual costs against planned costs and tracking budget performance throughout the project lifecycle.
  3. Allocate costs to individual project activities or work packages based on resource requirements, duration estimates, and other cost drivers. Ensure that costs are allocated in a way that aligns with project objectives, priorities, and resource constraints.
  4. Incorporate contingency reserves into the project budget to account for uncertainties and risks that may impact project costs. Reserve funds for unexpected expenses, scope changes, and other contingencies to mitigate the risk of cost overruns and budgetary variances.
  5. Implement cost monitoring and control mechanisms to track project expenditures, compare actual costs against planned costs, and identify budget variances. Use cost performance indicators such as Cost Performance Index (CPI) and Schedule Performance Index (SPI) to assess project cost and schedule efficiency.
  6. Manage changes to the project budget through a formal change control process. Evaluate proposed changes in terms of their impact on project costs, schedule, scope, and quality, and obtain appropriate approvals before implementing changes to the budget.
  7. Forecast future project costs based on current performance trends, anticipated changes in project scope or requirements, and other relevant factors. Use cost forecasting techniques such as Earned Value Management (EVM) to predict future project costs and assess the likelihood of meeting budget targets.
  8. Communicate cost information and updates to project stakeholders, ensuring that they are aware of budget status, variances, and potential cost impacts. Foster transparency and accountability by sharing cost reports, budget forecasts, and financial analyses with stakeholders regularly.

A plan can include risks inherent in the plan.

Including a risk management plan in the overall project plan is crucial for identifying, assessing, and managing risks that may affect the project’s success.By including risks inherent in the plan and implementing a comprehensive risk management approach, project managers can proactively identify and address potential threats and opportunities, minimize project disruptions, and enhance the likelihood of project success. A well-defined risk management plan helps mitigate uncertainty, optimize resource allocation, and improve overall project resilience and performance. Here’s how risks can be incorporated into a project plan:

  1. The first step in managing risks is to identify potential threats and opportunities that could impact the project’s objectives. This involves brainstorming sessions, risk workshops, and reviewing historical data to identify both internal and external risks that may arise during project execution.
  2. Once risks are identified, they need to be assessed to understand their potential impact and likelihood of occurrence. Use qualitative and quantitative risk assessment techniques to prioritize risks based on their severity and develop a risk register that documents each identified risk along with its probability and impact.
  3. After assessing risks, develop appropriate risk response strategies to mitigate, avoid, transfer, or accept each identified risk. For each risk, determine the most suitable response strategy that will minimize its impact on the project objectives and enhance the likelihood of project success.
  4. Develop contingency plans for high-impact risks that have the potential to significantly disrupt the project. Contingency plans outline specific actions to be taken if a risk materializes, ensuring that the project team is prepared to respond promptly and effectively to mitigate its impact.
  5. Clearly define roles and responsibilities for managing risks within the project team. Assign risk owners who are responsible for monitoring and addressing specific risks throughout the project lifecycle, ensuring accountability and oversight of risk management activities.
  6. Integrate risk management activities into the project’s planning, execution, and monitoring processes. Incorporate risk assessments, reviews, and updates into project milestones and deliverables to ensure that risk management remains an ongoing and proactive effort.
  7. Continuously monitor and review identified risks throughout the project lifecycle to assess their status and update risk responses as needed. Regularly review the risk register, assess emerging risks, and evaluate the effectiveness of risk mitigation strategies to ensure that the project remains on track.
  8. Communicate identified risks, their potential impact, and the corresponding risk responses to relevant stakeholders. Foster open communication channels to ensure that all project stakeholders are informed about potential risks and are aware of their roles and responsibilities in managing them.

A plan can include assumptions and constraints.

Including assumptions and constraints in a project plan is essential for providing clarity and context regarding the project’s operating environment and limitations. By including assumptions and constraints in the project plan, project managers can provide stakeholders with a clear understanding of the project’s operating context and limitations. This helps manage expectations, minimize misunderstandings, and facilitate effective decision-making and risk management throughout the project lifecycle. Here’s how assumptions and constraints can be incorporated into a project plan:

  1. Begin by identifying the key assumptions that underpin the project plan. Assumptions are factors or conditions that are considered to be true, accurate, or certain for planning but may not be guaranteed. These could include assumptions about resource availability, stakeholder behaviour, market conditions, technology readiness, or regulatory compliance.
  2. Document each assumption explicitly in the project plan, along with the rationale behind it and any potential implications if the assumption proves to be incorrect. Clearly stating assumptions helps ensure that all stakeholders have a shared understanding of the project’s underlying assumptions and the associated risks.
  3. Validate assumptions through research, analysis, or consultation with subject matter experts to confirm their accuracy and reliability. Challenge assumptions that are based on insufficient evidence or are subject to significant uncertainty to mitigate the risk of planning based on faulty assumptions.
  4. Similarly, identify the constraints that may impact the project’s execution or success. Constraints are limitations or restrictions that may impede the project’s ability to achieve its objectives, such as budgetary constraints, resource limitations, regulatory requirements, or time constraints.
  5. Document each constraint explicitly in the project plan, along with its specific impact on project activities and the corresponding risk mitigation strategies. Clearly articulating constraints helps project stakeholders understand the boundaries and limitations within which the project must operate.
  6. Continuously monitor and manage assumptions and constraints throughout the project lifecycle. Regularly review and reassess assumptions and constraints to ensure their continued validity and relevance in light of changing circumstances or new information.
  7. Communicate assumptions and constraints to all project stakeholders to ensure transparency and alignment. Communicate the potential implications of key assumptions and constraints on project planning, execution, and outcomes to facilitate informed decision-making and risk management.
  8. Update the project plan to reflect any changes or updates to assumptions and constraints as new information becomes available or as project circumstances evolve. Ensure that the project team remains aware of any changes and adapts their plans and actions accordingly.

Dependencies between activities and other work components (such as programmes and projects) should be defined.

Defining dependencies between activities and other work components is crucial for ensuring smooth project execution and managing interrelated tasks effectively. By defining and managing dependencies effectively in the project plan, project managers can minimize risks, optimize project scheduling and resource allocation, and enhance overall project performance and success. A well-defined approach to managing dependencies helps ensure that project activities are executed in a coordinated and integrated manner, ultimately leading to the achievement of project objectives and deliverables. Here’s how dependencies can be defined and managed in a project plan:

  1. Begin by identifying the dependencies between project activities, as well as any dependencies with external factors such as other projects, programs, or organizational processes. Dependencies can be of various types, including finish-to-start, start-to-start, finish-to-finish, and start-to-finish relationships.
  2. Document each identified dependency in the project plan, clearly specifying the nature of the dependency, the activities or components involved, and the directionality of the relationship. Use dependency mapping techniques such as network diagrams or dependency matrices to visualize and communicate dependencies effectively.
  3. Assess the impact of dependencies on project planning, scheduling, and resource allocation. Consider how delays or changes in one activity or component may affect the timing or success of dependent activities or components. Identify critical dependencies that have the potential to impact project objectives or deadlines significantly.
  4. Sequence project activities by the defined dependencies, ensuring that dependent activities are scheduled in the appropriate order to minimize delays and optimize resource utilization. Use scheduling tools and techniques such as the Critical Path Method (CPM) or Precedence Diagramming Method (PDM) to establish the logical sequence of activities based on dependency relationships.
  5. Proactively manage dependencies throughout the project lifecycle, monitoring their status and addressing any changes or disruptions promptly. Communicate dependencies to project stakeholders, ensuring that all team members are aware of their roles and responsibilities in managing interdependencies.
  6. Identify and mitigate risks associated with dependencies, such as delays, resource conflicts, or scope changes. Develop contingency plans or alternative strategies to address potential disruptions to dependent activities and minimize their impact on project outcomes.
  7. Collaborate with stakeholders, including project team members, program managers, and external partners, to manage dependencies effectively. Foster open communication channels to facilitate coordination, alignment, and collaboration among all parties involved in interrelated activities.
  8. Continuously monitor dependency relationships throughout the project lifecycle, tracking progress, identifying changes, and adjusting plans as needed to address evolving dependencies. Regularly review and update the project plan to reflect any changes in dependency relationships or project requirements.

The plan should include and allow for assurance and decision-making activities.

Assurance and decision-making activities are critical components of the project plan. These activities ensure that the project remains on track, aligns with organizational objectives, and meets stakeholder expectations. By including assurance and decision-making activities in the project plan, project managers can ensure that project performance, quality, and compliance are effectively monitored, managed, and improved throughout the project lifecycle. A well-defined approach to assurance and decision-making helps mitigate risks, enhance stakeholder confidence, and optimize project outcomes and benefits realization. Here’s how assurance and decision-making activities can be included in a project plan:

  1. Identify the key assurance activities that will be conducted throughout the project lifecycle to validate project progress, quality, and compliance with established standards and requirements. These activities may include reviews, audits, inspections, testing, and validation activities.
  2. Allocate the necessary resources, including personnel, tools, and time, to support assurance activities effectively. Ensure that qualified individuals or teams are assigned responsibility for conducting assurance activities and have the necessary expertise and authority to perform their roles effectively.
  3. Incorporate assurance activities into the project schedule, ensuring that they are conducted at appropriate milestones and intervals to provide timely feedback and insights into project performance and compliance. Coordinate assurance activities with project milestones and deliverables to minimize disruptions to project activities.
  4. Define clear decision-making processes and protocols for addressing issues, changes, and risks that arise during project execution. Establish criteria for decision-making, escalation paths, and decision authority levels to ensure that decisions are made in a timely and transparent manner.
  5. Document all decisions made throughout the project lifecycle, including the rationale behind each decision, the individuals involved, and any associated actions or follow-up activities. Maintain a decision log or register to track decisions, their status, and any related documentation or communications.
  6. Communicate the findings of assurance activities to relevant stakeholders, ensuring that project progress, quality, and compliance issues are transparently communicated and addressed. Provide stakeholders with timely updates on assurance findings and any corrective actions taken to address identified issues.
  7. Continuously monitor and review assurance activities to ensure that they are conducted effectively and deliver meaningful insights into project performance and compliance. Review assurance findings and recommendations regularly, making adjustments to assurance processes and protocols as needed to improve effectiveness and efficiency.
  8. Use assurance findings and decision-making processes to drive continuous improvement in project performance, quality, and governance. Identify trends, lessons learned, and opportunities for improvement based on assurance findings, and implement corrective actions and process enhancements to enhance project outcomes and mitigate risks.

The plan can be based on a hierarchy showing each work component’s place in the hierarchy with single-point accountability assigned for each work package and activity.

Using a hierarchical structure to organize work components in the project plan is a common and effective approach. This hierarchical structure helps to provide clarity, define responsibilities, and establish accountability throughout the project. By basing the project plan on a hierarchical structure and assigning single-point accountability for each work package and activity, project managers can effectively organize and manage the project’s work, clarify responsibilities, and enhance accountability throughout the project lifecycle. This hierarchical approach helps to ensure that project objectives are achieved efficiently and effectively, leading to successful project outcomes.Here’s how the hierarchical structure can be implemented in the project plan:

  1. Develop a Work Breakdown Structure (WBS) that decomposes the project scope into smaller, manageable work components or deliverables. The WBS represents a hierarchical breakdown of the project’s work into distinct levels, with each level representing a progressively detailed view of the project scope.
  2. Hierarchically organize the WBS, with higher-level components representing broader project phases or deliverables and lower-level components representing more detailed tasks or work packages. Each level in the hierarchy represents a logical grouping of related work components.
  3. Assign single-point accountability for each work package or activity within the WBS hierarchy. Clearly define the individual or team responsible for executing each work package and ensure that they have the authority and resources needed to complete the assigned tasks successfully.
  4. Document responsibility assignments within the WBS hierarchy, specifying the accountable individual or team for each work package or activity. This helps to establish clear lines of accountability and ensures that stakeholders understand their roles and responsibilities within the project.
  5. Ensure that single-point accountability is assigned at every level of the WBS hierarchy, from the highest-level project phases or deliverables down to the lowest-level tasks or work packages. This ensures that accountability is established at each level of the project’s work breakdown.
  6. Align the hierarchical structure of the project plan with the organizational structure of the project team. Ensure that reporting relationships, communication channels, and decision-making authority are consistent with the hierarchical organization of the project’s work components.
  7. Foster cross-functional collaboration and coordination within the hierarchical structure of the project plan. Encourage collaboration between different teams or departments responsible for executing related work components to ensure alignment and integration of efforts.
  8. Regularly review and update the hierarchical structure of the project plan as needed to reflect changes in project scope, priorities, or organizational structure. Ensure that accountability assignments remain current and aligned with project objectives throughout the project lifecycle.

Plans should be viewable at different levels of the hierarchy and show the level of detail appropriate to the needs of those viewing the plan.

Providing different views of the project plan at various levels of the hierarchy is essential for catering to the diverse needs of stakeholders and ensuring effective communication and understanding of project information.By offering plans that are viewable at different levels of the hierarchy and tailored to the needs of different stakeholders, project managers can ensure that project information is accessible, understandable, and actionable for all parties involved. This promotes transparency, alignment, and collaboration, ultimately contributing to the successful execution and delivery of the project. Here’s how plans can be viewable at different levels of the hierarchy:

  1. At the top level of the hierarchy, provide a high-level overview of the project plan that highlights key milestones, deliverables, and major phases or stages of the project. This summary view provides stakeholders with a broad understanding of the project’s scope, objectives, and timeline.
  2. Offer an intermediate level of detail that breaks down the project plan into manageable sections or work packages, providing more granularity while still maintaining a broader perspective. This level of detail allows stakeholders to delve deeper into specific areas of interest or concern without overwhelming them with unnecessary minutiae.
  3. Provide a detailed work breakdown that offers a comprehensive view of the project plan, including all tasks, activities, dependencies, and resource allocations at the lowest level of the hierarchy. This level of detail is useful for project team members and other stakeholders who require a thorough understanding of the project’s execution plan.
  4. Offer customized views of the project plan tailored to the specific needs and preferences of different stakeholders. For example, project sponsors may require a high-level summary view that focuses on project objectives and milestones, while project managers may need a more detailed view that includes task dependencies and resource assignments.
  5. Use visual representations such as Gantt charts, timelines, network diagrams, or Kanban boards to present the project plan in a clear and intuitive format. Visualizations help stakeholders quickly grasp complex information and identify critical paths, dependencies, and milestones within the project plan.
  6. Incorporate filtering and drill-down capabilities into the project management software or tools used to create and view the project plan. This allows stakeholders to filter information based on specific criteria or parameters and drill down into greater detail as needed.
  7. Ensure that the project plan is regularly updated and revised to reflect changes in project scope, objectives, or constraints. Communicate updates to stakeholders promptly and provide them with access to the most current version of the project plan to support informed decision-making and collaboration.
  8. Establish feedback mechanisms to solicit input and feedback from stakeholders on the usability and effectiveness of the project plan’s different views. Incorporate stakeholder feedback into ongoing improvements to the project plan and its presentation to enhance usability and relevance.

Planning should be iterative and progressive through the life cycle of a project, with more detail for the immediate future than for more distant work.

Adopting an iterative and progressive approach to planning is essential for effectively managing the dynamic nature of projects and adapting to changing circumstances and requirements throughout the project lifecycle. By adopting an iterative and progressive approach to planning, project managers can effectively manage uncertainty, respond to changing conditions, and maximize the likelihood of project success. This flexible planning approach allows for greater agility and adaptability, enabling projects to navigate complex challenges and deliver value to stakeholders efficiently. Here’s how planning can be iterative and progressive:

  1. Begin with an initial planning phase where the project scope, objectives, and high-level requirements are defined. This phase typically involves developing a project charter, conducting stakeholder analysis, and outlining the project’s goals and deliverables.
  2. Embrace progressive elaboration, which involves progressively adding detail to the project plan as more information becomes available and the project moves forward. Start with broad outlines and gradually refine the plan with more detail as the project progresses and uncertainty is reduced.
  3. Place more emphasis on planning for the immediate future, typically the next phase or iteration of the project. Develop detailed plans for upcoming activities, milestones, and deliverables while keeping future work at a higher level of abstraction.
  4. Adopt a just-in-time planning approach, where detailed planning is deferred until it’s necessary to make informed decisions or take action. Focus on planning activities that are critical to the next phase or iteration of the project, rather than trying to plan every aspect of the project upfront.
  5. Be prepared to adapt and adjust the project plan in response to changing requirements, priorities, and constraints. Continuously monitor project progress, gather feedback from stakeholders, and incorporate lessons learned to refine the plan and address emerging issues or opportunities.
  6. Conduct regular reviews and iterations of the project plan to ensure that it remains aligned with project objectives and stakeholders’ needs. Use feedback from reviews to identify areas for improvement, make adjustments to the plan, and course-correct as needed to keep the project on track.
  7. Integrate risk management into the planning process by identifying potential risks and developing mitigation strategies early in the project lifecycle. As the project progresses, continue to assess and manage risks, adjusting plans as necessary to address emerging threats or opportunities.
  8. Foster open communication and collaboration among project team members, stakeholders, and other relevant parties throughout the planning process. Encourage active participation in planning activities, solicit input and feedback from stakeholders, and ensure that everyone has a shared understanding of project objectives and priorities.

As work progresses, scope can be refined and clarified, to develop a plan which can be delivered at an acceptable level of risk.

Refining and clarifying the project scope as work progresses is a fundamental aspect of effective project management. This iterative process allows project teams to adapt to changing requirements, address emerging issues, and optimize project outcomes while managing risk appropriately.By actively refining and clarifying the project scope as work progresses, project teams can minimize ambiguity, reduce project risks, and enhance stakeholder satisfaction. This iterative approach to scope management allows projects to adapt to changing conditions, seize new opportunities, and deliver value to stakeholders effectively. Here’s how scope refinement and clarification can be achieved throughout the project lifecycle:

  1. Continuously validate and refine the project scope to ensure that it remains aligned with stakeholders’ needs and expectations. Regularly engage with stakeholders to gather feedback, clarify requirements, and address any discrepancies or misunderstandings regarding project scope.
  2. Conduct scope definition workshops or meetings with key stakeholders to collaboratively define and refine project scope. Use techniques such as brainstorming, mind mapping, or facilitated discussions to identify and prioritize project deliverables, features, and requirements.
  3. Embrace progressive elaboration to gradually expand and refine the project scope as more information becomes available and the project evolves. Start with a high-level scope statement and progressively add detail and clarity to the scope definition as the project progresses.
  4. Adopt an iterative approach to gathering and documenting project requirements, allowing for ongoing refinement and clarification based on evolving stakeholder needs and feedback. Use techniques such as user stories, use cases, or prototyping to capture and validate requirements iteratively.
  5. Implement a robust change control process to manage scope changes effectively and mitigate scope creep. Establish clear criteria for evaluating proposed changes, assess their impact on project objectives, and obtain appropriate approvals before incorporating changes into the project scope.
  6. Identify and assess risks associated with scope uncertainty or ambiguity and develop mitigation strategies to manage scope-related risks effectively. Proactively address potential scope challenges to minimize their impact on project timelines, budgets, and deliverables.
  7. Maintain open and transparent communication with stakeholders throughout the scope refinement process, keeping them informed of scope changes, updates, and decisions. Engage stakeholders in collaborative discussions to resolve scope-related issues and ensure alignment with project goals.
  8. Document all scope refinements, clarifications, and changes systematically to maintain a clear and comprehensive record of project scope evolution. Update project documentation, including the project scope statement, requirements documents, and work breakdown structure, to reflect the latest scope definition.

A plan may include an indication of the current level of certainty by, for example, using ranges or confidence indicators.

Indicating the current level of certainty in the project plan is crucial for managing expectations, making informed decisions, and effectively communicating project status to stakeholders. By including indications of the current level of certainty in the project plan, project managers can foster transparency, manage stakeholder expectations, and facilitate more informed decision-making in the face of uncertainty. This approach helps stakeholders understand the inherent risks and variability associated with project estimates and forecasts, enabling them to respond appropriately and effectively manage project execution. Here’s how ranges or confidence indicators can be used to convey the level of certainty:

  1. Instead of providing single-point estimates for project parameters such as cost, duration, or resource requirements, use estimation ranges to reflect the inherent uncertainty associated with these estimates. For example, instead of estimating a task to take precisely 5 days, provide a range such as 4-6 days to indicate the level of uncertainty.
  2. Use confidence intervals to quantify the level of confidence associated with project estimates or forecasts. Confidence intervals represent the range within which the true value of a parameter is likely to fall, based on the available data and assumptions. For instance, a cost estimate may be provided with a 90% confidence interval to indicate the level of certainty.
  3. Utilize probability distributions to model uncertainty and variability in project parameters. Probability distributions provide a more comprehensive representation of uncertainty by capturing the likelihood of different outcomes within a range. For example, a task duration may be modelled using a triangular distribution with minimum, most likely, and maximum estimates.
  4. Incorporate risk assessment results into the project plan to identify and quantify sources of uncertainty and their potential impact on project objectives. Use risk registers or heat maps to visualize the likelihood and severity of identified risks, providing stakeholders with insights into areas of high uncertainty.
  5. Introduce confidence indicators or qualitative descriptors to communicate the level of certainty associated with project estimates or assumptions. For instance, use terms such as “high,” “medium,” or “low” to indicate the degree of confidence in a particular estimate or forecast.
  6. Draw upon historical performance data from similar projects or past experiences to inform estimates and forecasts. Use benchmarks, reference class forecasting, or analogies to provide context and enhance the credibility of project estimates, considering the level of uncertainty associated with historical data.
  7. Conduct sensitivity analysis to assess the impact of uncertainty on project outcomes and identify critical factors driving uncertainty. Explore how variations in key assumptions or inputs affect project results, helping stakeholders understand the potential range of outcomes under different scenarios.
  8. Continuously update and refine the level of certainty indicators as the project progresses and additional information becomes available. Regularly review and reassess project estimates, assumptions, and risks to ensure that the level of certainty accurately reflects the current state of the project.